Proposals above the ceiling frustrate procurement of the polyclinic in Ponta Grossa

Tender previously required elaboration of projects and construction of the unit; notice of results was published on this Saturday (16)

PROJETO_POLICLINICA-4
#image_title
Advertisement

The bidding of the polyclinic in Ponta Grossa ended without hiring after the participating companies submitted proposals above the maximum value provided in the notice. The result was published by the City Hall in the Official Gazette of the Municipality on Friday (16).

The Electronic Competition No. 012/2026 aimed at hiring an engineering company specialized in developing executive projects and fully carry out the construction of a Specialized Attention Unit, identified in the document as a polyclinic.

Read also: Chamber votes opening of R$ 16.9 million for construction of polyclinic in Ponta Grossa

According to the notice, signed by the municipal secretary of Infrastructure, Luiz Henrique de Souza Honesko, the dispute was held on May 20, 2026. The result, dated October 15, informs that the tender was declared frustrated because the values presented by the interested bidders exceeded the established limit.

Proposals exceeded the budget

The justification presented in the document is financial: the proposals received were above the ceiling of the notice. Thus, the procedure did not result in the hiring of a company to develop the projects and execute the work. The notice does not detail how many companies participated in the competition, what were the prices offered or the maximum amount admitted by the municipal administration.

The publication also does not show the difference between the budget planned and the values of the proposals. The hiring was part of the bidding process No. 159/2026. The object was to gather both the elaboration of the executive projects and the integral execution of the construction of the health unit.

The next steps have not been reported

The published result does not inform whether the City Hall will make a new competition, review the budget or promote changes in the conditions of the hiring. There is also no new forecast for the start of the work. These definitions are necessary to clarify how the municipality intends to continue the project after the closure of the dispute without hiring.

The document does not allow to establish what the impact of the result will be on the schedule of the polyclinic. The publication is limited to communicating the result of the competition and the justification for it to have been declared frustrated.

Tags
Want to see BnT more often on Google?
Heryvelton Martins
Author
Heryvelton Martins
Jornalista formado pela Universidade Estadual de Ponta Grossa (UEPG) com experiência em jornalismo diário e cobertura política da região dos Campos Gerais do Paraná.
See all stories →
Advertisement
Advertisement
Related news
Web Stories
All →
VideosMore videos you might like
Watch on YouTube →
Part of the network
BnT OnlineNews portalCampos GeraisTravel appRádio BnTRadio · live
Viva Campos GeraisLong live Campos Gerais